The move to our new business premises is getting closer and closer and the building is now completely wind and watertight. This is important because the finishing and fitting out of the offices is in full swing. Construction is progressing according to plan and completion is scheduled for December 5 and so thereafter we can start the move.
Update of the construction work
The walls on the second floor are currently being finished with wallpaper and paint. The tiling and ceilings are finished and all of the sanitary appliances have been installed. This is followed by the first floor, where the walls are already in place. The walls are currently being placed on the ground floor along with the necessary electricity and data cabling.
The emergency stairs and the stairs from the canteen to the roof have been placed and will be followed by the other stairs. The main staircase at the entrance can only be placed once the high wall in the hall has been installed. This wall is 15.5 meters high!