Construction update of new business premises

We are working hard on the construction of our new business premises and it has now become clear we will receive the keys at the beginning of December. In January, we are moved to Honderdland 781, so we can make a fresh start in 2023 at our new workplace.

We are still on schedule with construction. The delivery of the round windows on the sides of the building was delayed, but these were also recently installed. This immediately creates a completely different look. The wall builders and fitters have worked hard during the construction industry holiday and soon the exterior doors, overhead doors and stairs will also be installed. The building is now almost completely fully glazed and watertight. The installation of the solar panels will start in two weeks.

Did you know that:

  • 913 have been used?
  • 800 tons of steel have been used in the building?
  • 200 m3 of concrete has been poured?
  • 450 tons of reinforcement has been used?
  • 20,000 H-pavers and 160,000 paving stones have been laid?

(13-09-2022)